Performance Report
Hello dear participants in the project of Aftab Taban Cooperative Company of Isfahan, we are happy to share the weekly report of Aftab Taban Company in the farmers' projects of the company for you.
1. Pool number one, its excavation has been completed and is ready for bed construction and operation.
2. The greenhouse hall number one of the first farm of Aftab Taban Cooperative Company of Isfahan is made of 90% plastic on the greenhouse and is ready for operation and planting of seedlings by mid-March.
3. In another week, the third phase will be ready for the foundation operation for the construction of the greenhouse.
4. Pool number two has started its bed-making operations, which will be completed within the next fifteen days.
5. The pool of the third number, including the digging of the wall, its strength operation has been completed and is ready for covering.
6. Branches including three-phase electricity have been put into operation at the project site. And there is a discussion about buying a gas branch, which will be installed next week, and its progress will be announced accordingly.
7. The contract for the construction of pool number four was also concluded and its construction will start next week.
8. In one hectare of land, the construction of the canal garden has been completed and in the middle of March, grape hair without seeds will be planted.
9. The guard building was completed and the guards were stationed in the mentioned place.
10. Salon number two of phase one is being prepared for seedling cultivation.
11. Purchase of "Five-hectare plastic" set number two, which was emptied in the project.
12. Ten percent of the heaters in the five-hectare complex number two were made and delivered to the complex.
13. The walls of the warehouses under construction, which have progressed up to sixty percent and the operation of the foundation, roof and columns has been completed, the builders of the foundation operation have been completed, and the formwork of the columns and the execution of the roof block joists will be completed. Until mid-March.
14. Excavation operations have been carried out in the amount of three and a half hectares in complex two.